Develop the network activity chart and identify the critical path for a project based on the following information. Redraw the activity network as a Gantt chart. What is the expected duration of the p

Develop the network activity chart and identify the critical path for a project based on thefollowing information. Redraw the activity network as a Gantt chart. What is the expectedduration of the project?Activity Expected Duration PredecessorsA 5 days B 6 days AC 2 days AD 4 days AE 6 days B, CF 6 days D, EG 12 days FH 4 days GI 6 days FJ 7 days H, I